Hi dears
New 3PAR 7400 4 Node assembled on a rack .
interconnect cables between Enclosures has been done But nothing doing about interconnect cables between Nodes (A & C).
Today an idiot powered on all enclosures and Nodes(even not correct order) .
consider No configuration.(Nothing till now)
Now what do i have to do ?
- power off all enclosures , complete cabling and powering on in correct order
or
- while it is powering on , attach cabling between interconnect Nodes and complete cabling (Not powering off)

Any suggestion ? (please DO NOT consider calling HP)

Author:  hdtvguy [ Mon May 05, 2014 5:49 am ]
Post subject:  Re: URGENT***Not complete Cabaling and power on****URGENT

I am not expert, but I don't think it is a huge deal, nothing is configured yet. At worst case the nodes will have a bunch of alerts. 2 options are wait for HP to get onsite and then have them serial in and cleanly shut down nodes or just power off.

Author:  Brewer [ Tue May 06, 2014 3:18 am ]
Post subject:  Re: URGENT***Not complete Cabaling and power on****URGENT

If the 7400 has no configuration (OOTB has not been run) then you can power it off, re cable, power on and run OOTB.